Chapter 18: Earned Value Management Questions
A Comprehensive Guide to Real-World Success
How do you calculate and interpret Cost Variance (CV) and Schedule Variance (SV) in Earned Value Management?
Cost Variance (CV) is calculated as Earned Value (EV) minus Actual Cost (AC). A positive CV indicates the project is under budget, while a negative CV suggests it's over budget. Schedule Variance (SV) is calculated as EV minus Planned Value (PV). A positive SV shows the project is ahead of schedule, and a negative SV means it’s behind schedule.
What is the difference between Cost Performance Index (CPI) and Schedule Performance Index (SPI), and how do you use them to assess project health?
The Cost Performance Index (CPI) is the ratio of EV to AC and reflects cost efficiency—values above 1 indicate the project is under budget, while values below 1 suggest it’s over budget. The Schedule Performance Index (SPI) is the ratio of EV to PV, showing schedule efficiency. An SPI greater than 1 indicates the project is ahead of schedule, while less than 1 means it’s behind.
Can you explain the significance of the Estimate at Completion (EAC) metric and describe how you calculate it using EVM?
Estimate at Completion (EAC) predicts the total cost of a project at completion, based on current performance. It is important for forecasting future budget requirements and ensuring the project stays within financial constraints. One common way to calculate EAC is by using the formula: EAC = Budget at Completion (BAC) divided by Cost Performance Index (CPI).
How would you address a situation where EVM metrics indicate a project is significantly over budget and behind schedule?
If EVM metrics show a project is over budget and behind schedule, corrective actions may include revising the project plan, reallocating resources, adjusting the scope, or modifying timelines. It’s crucial to identify root causes and implement strategies to optimize performance and bring the project back on track.
Describe a time when you used EVM to make a critical decision on a project. What was the outcome?
In a past project, EVM revealed significant cost overruns early in the process. Using this insight, I made the decision to reallocate resources and reprioritize tasks. This corrective action helped address the cost issues, and the project was completed on time and within budget, avoiding further delays and financial impact.
If the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.90, how is the project performing and why?
The project is over budget (CPI < 1) and behind schedule (SPI < 1). This indicates that the project is spending more than planned for the work completed and is progressing slower than expected.
A project has a CPI of 1.10 and an SPI of 0.95. What does this mean about the project's performance?
The project is under budget (CPI > 1) but slightly behind schedule (SPI < 1). This suggests cost efficiency but slower-than-planned progress.
Your project reports a CPI of 1.00 and an SPI of 1.20. How is the project doing, and what might this indicate about resource usage and schedule progress?
The project is on budget (CPI = 1) and ahead of schedule (SPI > 1). This indicates that the work is progressing faster than planned without exceeding the budget.
Close your knowledge gap
Understanding Earned Value Management (EVM), along with project finances and accounting, is crucial. If you’re unable to discuss these concepts confidently in an interview, it’s important to address this knowledge gap. You need to have a solid grasp of project accounting principles, as EVM is just one tool in a larger framework. If you recognize this as a weakness, I highly recommend taking the time to improve your understanding.
Visit our website blog and reed free articles on EVM that you can use to enhance your knowledge. Additionally, we offer a comprehensive advanced project management course. If those options don’t work for you, consider exploring project accounting or advanced project management courses at a college or university you prefer.
AI for Agile Project Managers and Scrum Masters
Become an AI-first leader and transform your agile practice by leveraging artificial intelligence as your most powerful co-pilot. This course is designed to help you drive efficiency, insight, and innovation, ensuring you stay at the forefront of a rapidly evolving project management landscape.
This isn't about replacing human intuition—it's about augmenting it. You'll master prompt engineering to automate mundane tasks, freeing up your time for high-impact strategic leadership and creative problem-solving. Learn to refine backlogs, create strategic roadmaps, and integrate AI seamlessly into your agile ceremonies.
Gain predictive power by using AI-driven insights to anticipate project risks and seize new opportunities for more reliable outcomes. We deliver practical, prompt-based workflows and proven strategies built around real-world agile challenges that you can implement immediately within your framework.
Master foundational AI concepts specifically relevant to Scrum environments while developing advanced skills to handle diverse agile scenarios. You will learn to champion an AI-enabled culture within your organization, fostering a dynamic environment of continuous improvement and superior team delivery.
Ready to lead the future of agile and make data-driven decisions that cut through complexity? Join a community of forward-thinking professionals and position yourself as an indispensable leader in the AI era. Enroll now and unlock your future!
Become an AI-First Agile Leader!
HK School of Management empowers you to master AI as your most powerful co-pilot—without the complexity. Transform your agile leadership with practical, prompt-based workflows and proven strategies designed for real-world scrum challenges. For the price of lunch, you get the tools to automate mundane tasks, refine backlogs with precision, and drive unprecedented efficiency in your team. Backed by our 30-day money-back guarantee—zero risk, real impact.
Learn More
HKSM